Suggestions based on the Question and Answer that you are currently viewing
Define process capability.
How is a process operating in statistical control distinguished from one that is not?
\r\n
What are the two principal aspects of product quality?
\r\n
Five jobs are waiting to be scheduled on a machine. For order A, the remaining process time = 5
\r\ndays, and the due date is day 8. For order B, the remaining process time = 7 days, and the due
\r\ndate is day 16. For order C, the remaining process time = 11 days, and the due date is day 22. For
\r\norder D, the remaining process time = 9 days, and the due date is day 31. For order E, the
\r\nremaining process time = 10 days, and the due date is day 26. Determine a production schedulebased on (a) shortest processing time, (b) earliest due date, (c) critical ratio, and (d) least slack time.
\r\nAll times are listed in days.
The current date in the production calendar is day 14. There are three orders (A, B, and C) to be
\r\nprocessed at a particular work center. The orders arrived in the sequence A-B-C at the work
\r\ncenter. For order A, the remaining process time = 8 days, and the due date is day 24. For order B,
\r\nthe remaining process time = 14 days, and the due date is day 33. For order C, the remaining
\r\nprocess time = 6 days, and the due date is day 26. Determine the sequence of the orders that
\r\nwould be scheduled using (a) first-come-first-serve, (b) earliest due date, (c) shortest processing
\r\ntime, (d) least slack time, and (e) critical ratio.
In the previous problem, propose a way of scheduling to meet the weekly demand if there were four
\r\nmachines instead of three.
Four products are to be manufactured in Department A, and it is desired to determine how to
\r\nallocate resources in that department to meet the required demand for these products for a certain
\r\nweek. For product 1, demand = 750/wk, setup time = 6 hr, and operation time = 4.0 min. For
\r\nproduct 2, demand = 900/wk, setup time = 5 hr, and operation time = 3.0 min. For product 3,
\r\ndemand = 400/wk, setup time = 7 hr, and operation time = 2.0 min. For product 4, demand =
\r\n400/wk, setup time = 6 hr, and operation time = 3.0 min. The plant normally operates one shift
\r\n(7.0 hours per shift), five days per week and there are currently 3 work centers in the department.
\r\nPropose a way of scheduling the machines to meet the weekly demand.
\r\n
Solve Problem 41.9 except that the following is known in addition to the information given:
\r\nscheduled receipts of M5 are 250 units in period (week) 3 and 50 units in period (week) 4.
\r\n
Requirements are to be planned for component C5 in product P1. Required deliveries for P1 are
\r\ngiven in Table 41.1. Ordering, manufacturing, and assembly lead times are as follows: for P1 and
\r\nS2, the lead time is one week; for C5, the lead time is three weeks; and for M5, the lead time is 2
\r\nweeks. Given the product structure in Figure 41.4, determine the time-phased requirements for M5,
\r\nC5, and S2 to meet the master schedule for P1. Assume no common use items. On-hand inventories
\r\nare 200 units for M5 and 100 units for C5, zero for S2. Use a format similar to Table 41.2 and
\r\ndevelop a spreadsheet calculator to solve. Ignore demand for P1 beyond period 10.
Quantity requirements are to be planned for component C2 in product P1. Required deliveries for
\r\nP1 are given in Table 41.1. Ordering, manufacturing, and assembly lead times are as follows: for
\r\nP1 and C2, the lead time is one week; and for S1 and M2, the lead time is two weeks. Given the
\r\nproduct structure in Figure 41.4, determine the time-phased requirements for M2, C2, and S1 to
\r\nmeet the master schedule for P1. Assume no common use items and all on-hand inventories and
\r\nscheduled receipts are zero. Use a format similar to Table 41.2 and develop a spreadsheet
\r\ncalculator to solve. Ignore demand for P1 beyond period 10.
The two-bin approach is used to control inventory for a particular low-cost component. Each bin
\r\nholds 1200 units. The annual usage of the component is 45,000 units. Cost to order the component
\r\nis around $70. (a) What is the imputed holding cost per unit for this data? (b) If the actual annual
\r\nholding cost per unit is only 7 cents, what lot size should be ordered? (c) How much more is the
\r\ncurrent two-bin approach costing the company annually, compared to the economic order quantity?
Current setup time on a certain machine is 3.0 hr. Cost of downtime on this machine is estimated at
\r\n$200/hr. Annual holding cost per part made on the equipment, Ch = $1.00. Annual demand for the
\r\npart is 15,000 units. Determine (a) EOQ and (b) total inventory costs for this data. Also, determine
\r\n(c) EOQ and (d) total inventory costs, if the changeover time could be reduced to six minutes.
A certain piece of production equipment is used to produce various components for an assembled
\r\nproduct. To keep in-process inventories low, it is desired to produce the components in batch sizes
\r\nof 150 units. Demand for each product is 2500 units per year. Production downtime costs an
\r\nestimated $200/hr. All of the components made on the equipment are of approximately equal unit
\r\ncost, which is $9.00. Holding cost rate = 30%/yr. In how many minutes must the changeover
\r\nbetween batches be completed in order for 150 units to be the economic order quantity?
\r\n
Assembly of a product requires that a component part be ordered and stocked. Demand for the
\r\nproduct is constant throughout the year at 7800 units annually. The cost to place an order is $95.
\r\nThe cost of the part is $56 and the holding cost rate is 22%. When units are ordered, they take two
\r\nweeks to arrive. Determine (a) the economic order quantity and (b) the reorder point. (c) The parts
\r\nare prepackaged in multiples of 100. It saves the supplier unpacking and repackaging time if they
\r\ncan ship in multiples of 100. The supplier has offered to reduce the price by $1 per unit if even
\r\nmultiples of 100 are purchased. How much would be saved (if anything) by taking this offer?
\r\n
A product is produced in batches. Batch size = 2000 units. Annual demand = 50,000 units, and unit
\r\ncost of the product = $4.00. Setup time to run a batch = 2.5 hr, cost of downtime on the affected
\r\nequipment is figured at $250/hr, and annual holding cost rate = 30%. What would the annual
\r\nsavings be if the product were produced in the economic order quantity?
\r\n
Given that annual demand for a product is 20,000 units, cost per unit = $6.00, holding cost rate =
\r\n2.5%/month, changeover (setup) time between products averages 2.0 hr, and downtime cost during
\r\nchangeover = $200/hr, determine (a) economic order quantity and (b) total inventory costs for this
\r\nsituation.
A product is made to stock. Annual demand is 86,000 units. Each unit costs $9.50 and the annual
\r\nholding cost rate is 22%. Setup cost to produce this product is $800. Determine (a) economic order
\r\nquantity and (b) total inventory costs for this situation.
\r\n
There are 15 correct answers in the following multiple choice questions (some questions have multiple
\r\nanswers that are correct). To attain a perfect score on the quiz, all correct answers must be given. Each
\r\ncorrect answer is worth 1 point. Each omitted answer or wrong answer reduces the score by 1 point, and
\r\neach additional answer beyond the correct number of answers reduces the score by 1 point. Percentage
\r\non the quiz is based on the total number of correct answers.
\r\n41.1 Which one of the following terms best describes the overall function of production planning and
\r\ncontrol: (a) inventory control, (b) manufacturing logistics, (c) manufacturing engineering, (d) mass
\r\nproduction, or (e) product design?
\r\n41.2 Which of the following are the three categories of items usually listed in the master production
\r\nschedule: (a) components used to build the final products, (b) firm customer orders, (c) general
\r\nproduct lines, (d) orders for maintenance and spare parts, (e) sales forecasts, and (f) spare tires?
\r\n41.3 Inventory carrying costs include which of the following (two best answers): (a) equipment
\r\ndowntime, (b) interest, (c) production, (d) setup, (e) spoilage, (f) stock-out, and (g) storage?
\r\n41.4 Which of the following are the three terms in the economic order quantity formula: (a) annual
\r\ndemand rate, (b) batch size, (c) cost per piece, (d) holding cost, (e) interest rate, and (f) setup cost?
\r\n41.5 Order point inventory systems are intended for which of the following (two best answers): (a)
\r\ndependent demand items, (b) independent demand items, (c) low production quantities, (d) mass
\r\nproduction quantities, and (e) mid-range production quantities?
\r\n41.6 With which of the following manufacturing resources is capacity requirements planning primarily
\r\nconcerned (two best answers): (a) component parts, (b) direct labor, (c) inventory storage space, (d)
\r\nproduction equipment, and (e) raw materials?
\r\n41.7 The word kanban is most closely associated with which one of the following: (a) capacity planning,
\r\n(b) economic order quantity, (c) just-in-time production, (d) master production schedule, or (e)
\r\nmaterial requirements planning?
\r\n41.8 Machine loading refers most closely to which one of the following: (a) assigning jobs to a work
\r\ncenter, (b) floor foundation in the factory, (c) managing work-in-process in the factory, (d) releasing
\r\norders to the shop, or (e) sequencing jobs through a machine?
\r\n
What are the three phases in shop floor control?
\r\n
How is a pull system distinguished from a push system in production and inventory control?
Identify the principal objective in just-in-time production.
\r\n
What are some of the resource changes that can be made to increase plant capacity in the short run?
\r\n
Identify the inputs to the MRP processor in material requirements planning.
\r\n
In MRP, what are common use items?
Define reorder point inventory system.
The benefits of buying with AnswerDone:
Access to High-Quality Documents
Our platform features a wide range of meticulously curated documents, from solved assignments and research papers to detailed study guides. Each document is reviewed to ensure it meets our high standards, giving you access to reliable and high-quality resources.
Easy and Secure Transactions
We prioritize your security. Our platform uses advanced encryption technology to protect your personal and financial information. Buying with AnswerDone means you can make transactions with confidence, knowing that your data is secure
Instant Access
Once you make a purchase, you’ll have immediate access to your documents. No waiting periods or delays—just instant delivery of the resources you need to succeed.