The current date in the production calendar is day 14. There are three orders (A, B, and C) to be\nprocessed at a particular work center. The orders ar
The current date in the production calendar is day 14. There are three orders (A, B, and C) to be
\r\nprocessed at a particular work center. The orders arrived in the sequence A-B-C at the work
\r\ncenter. For order A, the remaining process time = 8 days, and the due date is day 24. For order B,
\r\nthe remaining process time = 14 days, and the due date is day 33. For order C, the remaining
\r\nprocess time = 6 days, and the due date is day 26. Determine the sequence of the orders that
\r\nwould be scheduled using (a) first-come-first-serve, (b) earliest due date, (c) shortest processing
\r\ntime, (d) least slack time, and (e) critical ratio.