Shanahan Construction Company has entered into a contract beginning January 1, 2014, to build a parking complex. It has been estimated that the comple
Shanahan Construction Company has entered into a contract beginning January 1, 2014, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2014 2015 2016
\r\nCosts to date $270,000 $450,000 $610,000
\r\nEstimated costs to complete 330,000 150,000 –0–
\r\nProgress billings to date 270,000 550,000 900,000
\r\nCash collected to date 240,000 500,000 900,000
\r\nInstructions
\r\n(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
\r\n(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.