Quantity requirements are to be planned for component C2 in product P1. Required deliveries for\nP1 are given in Table 41.1. Ordering, manufacturing, a
Quantity requirements are to be planned for component C2 in product P1. Required deliveries for
\r\nP1 are given in Table 41.1. Ordering, manufacturing, and assembly lead times are as follows: for
\r\nP1 and C2, the lead time is one week; and for S1 and M2, the lead time is two weeks. Given the
\r\nproduct structure in Figure 41.4, determine the time-phased requirements for M2, C2, and S1 to
\r\nmeet the master schedule for P1. Assume no common use items and all on-hand inventories and
\r\nscheduled receipts are zero. Use a format similar to Table 41.2 and develop a spreadsheet
\r\ncalculator to solve. Ignore demand for P1 beyond period 10.