Production rate for a certain assembled product is 47.5 units per hour. The total assembly work\ncontent time = 32 minutes of direct manual labor. The
Production rate for a certain assembled product is 47.5 units per hour. The total assembly work
\r\ncontent time = 32 minutes of direct manual labor. The line operates at 95% uptime. Ten
\r\nworkstations have two workers on opposite sides of the line so that both sides of the product can be
\r\nworked on simultaneously. The remaining stations have one worker. Repositioning time lost by
\r\neach worker is 0.2 min/cycle. It is known that the number of workers on the line is two more than
\r\nthe number required for perfect balance. Determine (a) number of workers, (b) number of
\r\nworkstations, (c) the balancing efficiency, and (d) average manning level.