On January 1, 2014, Blair Corporation purchased for $500,000 a tract of land (site number 101) with a building. Blair paid a real estate broker’s comm
On January 1, 2014, Blair Corporation purchased for $500,000 a tract of land (site number 101) with a building. Blair paid a real estate broker’s commission of $36,000, legal fees of $6,000, and title guarantee insurance of $18,000. The closing statement indicated that the land value was $500,000 and the building value was $100,000. Shortly after acquisition, the building was razed at a cost of $54,000.
\r\nBlair entered into a $3,000,000 fixed-price contract with Slatkin Builders, Inc. on March 1, 2014, for the construction of an office building on land site number 101. The building was completed and occupied on
\r\nSeptember 30, 2015. Additional construction costs were incurred as follows.
\r\nPlans, specifi cations, and blueprints $21,000
\r\nArchitects’ fees for design and supervision 82,000
\r\nThe building is estimated to have a 40-year life from date of completion and will be depreciated using the 150% declining-balance method.
\r\nTo finance construction costs, Blair borrowed $3,000,000 on March 1, 2014. The loan is payable in 10 annual installments of $300,000 starting on March 1, 2015, plus interest at the rate of 10%. Blair’s weighted-average amounts of accumulated building construction expenditures were as follows.
\r\nFor the period March 1 to December 31, 2014 $1,300,000
\r\nFor the period January 1 to September 30, 2015 1,900,000
\r\nInstructions
\r\n(a) Prepare a schedule that discloses the individual costs making up the balance in the land account in respect of land site number 101 as of September 30, 2015.
\r\n(b) Prepare a schedule that discloses the individual costs that should be capitalized in the office building account as of September 30, 2015 Show supporting computations in good form.