In the previous problem, suppose an industrial robot cell were installed to replace the welder. The\ncell consists of the robot (using GMAW instead of
In the previous problem, suppose an industrial robot cell were installed to replace the welder. The
\r\ncell consists of the robot (using GMAW instead of SMAW or FCAW), two welding fixtures, and
\r\nthe fitter who loads and unloads the parts. With two fixtures, fitter and robot work simultaneously,
\r\nthe robot welding at one fixture while the fitter unloads and loads at the other. At the end of each
\r\nwork cycle, they switch places. The electrode wire spool must be changed every five workparts,
\r\nwhich task requires 5.0 minutes and is accomplished by the fitter. Determine (a) arc time and (b)
\r\nproduction rate for this work cell.