Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2014, Hamilton began work under contract #E2-D2, which provid
Hamilton Construction Company uses the percentage-of-completion method of accounting. In 2014, Hamilton began work under contract #E2-D2, which provided for a contract price of $2,200,000. Other details follow: 2014 2015
\r\nCosts incurred during the year $640,000 $1,425,000
\r\nEstimated costs to complete, as of December 31 960,000 –0–
\r\nBillings during the year 420,000 1,680,000
\r\nCollections during the year 350,000 1,500,000
\r\nInstructions
\r\n(a) What portion of the total contract price would be recognized as revenue in 2014? In 2015?
\r\n(b) Assuming the same facts as those above except that Hamilton uses the completed-contract method of accounting, what portion of the total contract price would be recognized as revenue in 2015?
\r\n(c) Prepare a complete set of journal entries for 2014 (using the percentage-of-completion method).