Five jobs are waiting to be scheduled on a machine. For order A, the remaining process time = 5\ndays, and the due date is day 8. For order B, the rema
Five jobs are waiting to be scheduled on a machine. For order A, the remaining process time = 5
\r\ndays, and the due date is day 8. For order B, the remaining process time = 7 days, and the due
\r\ndate is day 16. For order C, the remaining process time = 11 days, and the due date is day 22. For
\r\norder D, the remaining process time = 9 days, and the due date is day 31. For order E, the
\r\nremaining process time = 10 days, and the due date is day 26. Determine a production schedulebased on (a) shortest processing time, (b) earliest due date, (c) critical ratio, and (d) least slack time.
\r\nAll times are listed in days.