Berstler Construction Company began operations in 2014. Construction activity for the first year is shown below. All contracts are with different cust
Berstler Construction Company began operations in 2014. Construction activity for the first year is shown below. All contracts are with different customers, and any work remaining at December 31, 2014, is expected to be completed in 2015.
\r\nCash Contract Estimated
\r\nTotal Billings Collections Costs Incurred Additional
\r\nContract through through through Costs to
\r\nProject Price 12/31/14 12/31/14 12/31/14 Complete
\r\n1 $ 560,000 $ 360,000 $340,000 $450,000 $130,000
\r\n2 670,000 220,000 210,000 126,000 504,000
\r\n3 520,000 500,000 440,000 330,000 –0–
\r\n$1,750,000 $1,080,000 $990,000 $906,000 $634,000
\r\nInstructions
\r\nPrepare a partial income statement and balance sheet to indicate how the above information would be reported for financial statement purposes. Berstler Construction Company uses the completed-contract method.