A single model manual assembly line produces a product whose work content time = 47.8 min. The\nline has 24 workstations with a manning level = 1.25. A
A single model manual assembly line produces a product whose work content time = 47.8 min. The
\r\nline has 24 workstations with a manning level = 1.25. Available shift time per day = 8 hr, but
\r\ndowntime during the shift reduces actual production time to 7.6 hr on average. This results in an
\r\naverage daily production of 256 units/day. Repositioning time per worker is 8% of cycle time.
\r\nDetermine (a) line efficiency, (b) balancing efficiency, and (c) repositioning time.