A manual assembly line is being designed for a product with annual demand = 100,000 units. The\nline will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/
A manual assembly line is being designed for a product with annual demand = 100,000 units. The
\r\nline will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/shift. Work units will be attached to a
\r\ncontinuously moving conveyor. Work content time = 42.0 min. Assume line efficiency = 0.97,
\r\nbalancing efficiency = 0.92, and repositioning time = 6 sec. Determine (a) hourly production rate to
\r\nmeet demand, (b) number of workers required, and (c) the number of workstations required if the
\r\nestimated manning level is 1.4.