Problem NO: 1

A manual assembly line is being designed for a product with annual demand = 100,000 units. The\nline will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/

A manual assembly line is being designed for a product with annual demand = 100,000 units. The

\r\n

line will operate 50 wks/year, 5 shifts/wk, and 7.5 hr/shift. Work units will be attached to a

\r\n

continuously moving conveyor. Work content time = 42.0 min. Assume line efficiency = 0.97,

\r\n

balancing efficiency = 0.92, and repositioning time = 6 sec. Determine (a) hourly production rate to

\r\n

meet demand, (b) number of workers required, and (c) the number of workstations required if the

\r\n

estimated manning level is 1.4.

0  reviews

Suggestions based on the Question and Answer that you are currently viewing

The benefits of buying with AnswerDone:

Guaranteed quality through customer reviews

Access to High-Quality Documents

Our platform features a wide range of meticulously curated documents, from solved assignments and research papers to detailed study guides. Each document is reviewed to ensure it meets our high standards, giving you access to reliable and high-quality resources.

Quick and easy check-out

Easy and Secure Transactions

We prioritize your security. Our platform uses advanced encryption technology to protect your personal and financial information. Buying with AnswerDone means you can make transactions with confidence, knowing that your data is secure

Focus on what matters

Instant Access

Once you make a purchase, you’ll have immediate access to your documents. No waiting periods or delays—just instant delivery of the resources you need to succeed.

$1.49  0x  sold
    (0)
  Add to cart