A 7-station transfer line has been observed over a 40-hour period. The process times at each\nstation are as follows: station 1, 0.80 min; station 2, 1
A 7-station transfer line has been observed over a 40-hour period. The process times at each
\r\nstation are as follows: station 1, 0.80 min; station 2, 1.10 min; station 3, 1.15 min; station 4, 0.95
\r\nmin; station 5, 1.06 min; station 6, 0.92 min; and station 7, 0.80 min. The transfer time between
\r\nstations = 6 sec. The number of downtime occurrences = 110, and hours of downtime = 14.5
\r\nhours. Determine (a) the number of parts produced during the week, (b) the average actual
\r\nproduction rate in parts/hour, and (c) the line efficiency. (d) If the balancing efficiency were
\r\ncomputed for this line, what would its value be?